Scheduled maintenance in Carlow Data centre Monday 8th of April
We will be transferring power to generator/UPS in the Carlow data centre on Friday 29th to accommodate power upgrades to the site. This will
We will be transferring power to generator/UPS in the Carlow data centre on Friday 29th to accommodate power upgrades to the site. This will
SIRO have reported that the outage in the Kildare area is now resolved. (https://twitter.com/SIROIreland/status/1755972976950857773) The issue occurred due to excavation works by another party
We will be performing a scheduled upgrade of our Cloud storage platform with our partners NetApp, starting at 06:00 February 14th. NetApp have advised
Summary: Plesk003 shared hosting server is offline this morning, Engineers are working to resolve the issue and are also restoring a backup from last